The residential building on Rambla Montserrat in Cerdanyola that we started in May is progressing at a good pace. Last month we finished the structure, we are currently in the phase of masonry, enclosures and systems and in January the phase of finishes will begin. The four apartments, parking spaces and storage rooms are already sold, and the expected delivery date is the 2nd quarter of 2019.